Utilities [1]: New 9km water main to cut across Romney Marsh - (Map) [2]
Posted by editor on Feb 09, 2012 - 05:55 AM
[3]
|
A route for a
new 9km strategic water main across Romney Marsh has now been agreed
after extensive research and consultation on environmental impacts.
|
 |
|
It will run from the Denge Water Treatment Works near Lydd to St Mary’s
Bay avoiding wherever possible sensitive environmental areas.
Work on the £5m project is due to begin in the early summer and the main
will be in operation in 2014.
The new main will replace an older pipeline which has been assessed as
having a high risk of bursts. Completion will ensure greater security of
supply for the Romney Marsh area.
In 2012 construction of the main between St Mary’s Bay and New Romney
will be completed and in 2013 between New Romney and the Denge Water
Treatment Works.
Veolia Water Southeast Capital Delivery Manager Justin Southwell said
detailed and rigorous planning had ensured that the selected route would
minimise environmental impacts.
He said: “We have a great deal of experience in working in sensitive
areas on Romney Marsh and we are confident that we now have a good route
for the pipeline. We brought in independent environmental consultants to
undertake research and advise on route planning and we have worked
closely with Natural England.”
Most of the pipeline route runs across farmland with a small part of New
Romney being the only urban area affected.

A playground in Station Road will be directly affected and will be
closed while the pipeline is laid through it. The adjacent playing field
will be able to remain open though works will affect the edge of the
playing field area. Single lane working in Station Road and Church Lane
in New Romney will be needed for brief periods.
The pipeline will cross Lydd Golf Course and several holes will be
affected. Discussions are underway with the golf course management. A
small part of Littlestone Golf Course too will be affected but this
should have no impact on play with all holes remaining safely open.
The pipeline will also cross the Romney Hythe and Dymchurch Railway and
an approach for this is being agreed well in advance with RHDR. There
will be a need to restrict services on part of the line for a few days
and this work will be undertaken in November to minimise inconvenience.
An alternative bus service for schoolchildren and students who use the
line at that time of year is being discussed.
The route passes close to the boundaries of Lydd Airport and discussions
have been held with airport management. Airport operations will continue
as usual during construction work.
The mains scheme is part of Veolia Water Southeast’s £34.5m capital
investment programme for the five years to 2015. This programme also
includes the linked upgrading of Denge Water Treatment Works which is
already underway and scheduled for completion early in 2013.
Justin Southwell added: “We are undertaking a major programme to improve
the security of supply on Romney Marsh while delivering the highest
quality water at the tap.
“Earlier projects included the building of some 14kms of new mains
between Cheriton and St Mary’s Bay. This now gives us the ability to
bring in water from the Folkestone area should any problem occur in
local sources on Romney Marsh such as intrusion by seawater.”