Faulty equipment delays erection

Posted by editor on Jun 18, 2008 - 09:00 AM
Filed under: Environment, News

News

Erection of the 26 giant turbines at a new £60m  wind farm on Romney Marsh has begun after a delay caused by problems with the giant crane lifting the components into place.

In preparation for the assembly of the 115m-high turbines, the German-made propeller blades had been transported in 78 lorries across Kent from Chatham docks.

Two turbines will be erected every week until the end of September.

Once online, the wind farm, which received planning approval in 2005 after local opposition and a public inquiry, will generate enough electricity to power 33,000 UK homes.





 

Comments

Display Order
Faulty equipment delays erection
by finkle
on Jun 18, 2008
[ _USERINFO ] [ _SENDAMSG ]

Faulty equipment delays erection, oh please!

Hoping for a mention on Radio Four's news Quiz, Ed ?

Quite Good Quite Good

Get Pfizer involved?

Finkle get me coat now!


Only logged in users are allowed to comment. register/log in

 

Find it fast

  • Home
  • Just local news
  • Just letters
  • Just comments
  • News archive
  • About us
  • Terms of use
  • Privacy policy
  • Search
 
 

 
 

 
 

+ Bookmark

Email us localrags@gmail.com


Please follow the instructions to add us to your bookmarks... Thank you...

 
 

Members

 

  • New account registration
  • Lost password recovery
 
 

Find your HOLIDAY bargains here!

 
 

Community Centre Specials!

 
 

Top Ten stories...

.....read more Stories...

 
 

VISIT US ON FACEBOOK.....

 

© 2012 Hawkinge Gazette. Design by Flashdaweb RSS RSS | Atom Atom | Terms of use | Contact | Zikula | YAML |